How Much Does It Cost to Pave a Parking Lot in Georgia?
National cost guides put a new asphalt parking lot at about $3 to $7 per square foot. By the stall, it runs about $900 to $2,500. A lot takes about 300 to 350 square feet per car once the aisles and entrances are counted.
Resurfacing a sound lot runs about $1 to $3 per square foot, or $300 to $900 per space. Sealcoating runs about $0.14 to $0.25 per square foot. Striping runs about $4 to $5 per standard stall and $25 to $40 per accessible stall. A 30 to 50 stall lot runs about $500 to $1,200 to stripe.
These are market numbers from national cost guides, not our price list. In Georgia, also watch Georgia DOT’s monthly price for the liquid asphalt in the mix.
What drives the cost to pave a parking lot?
These are the things that move the price of parking lot paving.
Lot size. Guides price lots by the square foot or by the stall.
New lot, resurfacing or repair. A new lot is built from the ground up. Each job has its own range in the table below.
Base work and drainage. Before any asphalt goes down, we grade the site for drainage, then put down the stone base and compact it. More grading and more stone mean a higher price.
Thickness for truck traffic. Lanes where delivery trucks run need a heavier section than the car stalls.
Access and phasing. A business that stays open during the work needs the lot paved in sections. We plan the work in phases with you, and the plan belongs in the estimate.
Striping and accessible spaces. The stall layout and the accessible spaces set how much paint goes down. Our guides to parking space dimensions in Georgia and ADA parking space requirements cover the sizes and the counts.
Site plans and permits. One national guide says to plan for permits, striping and sealcoating on top of the paving number. A new lot on bare ground can also need site plans and a land disturbance permit. Ask the city or county what your site needs before the work starts. We build to the approved plan.
What does an asphalt parking lot cost per square foot?
Every figure below is a market number from national cost guides, not our price list.
| Job | Market range | Source |
|---|---|---|
| New asphalt lot | $3 to $7 per square foot | National cost guide; a second guide says $2.50 to $7 |
| New asphalt lot, per stall | $900 to $2,500 per stall | National cost guide, at 300 to 350 square feet per car |
| Resurfacing | $1 to $3 per square foot, or $300 to $900 per space | National cost guide |
| Repair | $2 to $5 per square foot | National cost guide |
| Sealcoating | $0.14 to $0.25 per square foot | National cost guide |
| Striping, standard stall | $4 to $5 per stall | National cost guide |
| Striping, accessible stall | $25 to $40 per stall | National cost guide |
| Striping, 30 to 50 stall lot | $500 to $1,200, arrows and crosswalks included | National cost guide |
For whole projects, one national guide says most parking lots land between $10,000 and $150,000.
What would a 50-space parking lot cost?
Here is the market math for a 50-space lot, from the ranges above. It is an example, not a quote. At 300 to 350 square feet per car, 50 spaces come to about 15,000 to 17,500 square feet.
| Job on a 50-space lot | Market rate | Market math |
|---|---|---|
| New asphalt lot | $3 to $7 per square foot | $45,000 to $122,500 |
| Resurfacing | $1 to $3 per square foot | $15,000 to $52,500 |
| Sealcoating | $0.14 to $0.25 per square foot | $2,100 to $4,375 |
| Striping | 30 to 50 stall lot | $500 to $1,200 |
The per-stall figure lands close by. At $900 to $2,500 a stall, 50 stalls come to $45,000 to $125,000 for a new lot. A real lot’s base and drainage decide where it falls.
Why did asphalt prices jump in Georgia in 2026?
Georgia DOT publishes a monthly asphalt cement price, the Georgia Base Asphalt Price. It is an average of posted supplier prices for asphalt cement, the liquid binder that holds the stone together. It is not the price of finished hot mix.
The index read $577 a ton in November 2025 and $559 in March 2026. By June 2026 it reached $721, a jump of about 29 percent in three months. It stood at $700 in November 2026, up about 21 percent from a year earlier.
Georgia DOT uses the index for payments on its eligible projects. Hot mix is stone and sand mixed with asphalt cement at an asphalt plant. The binder is one input in its price, so a jump like spring 2026’s can show up in paving bids. That is one more reason a written estimate should say what it includes.
Should you resurface or replace a parking lot?
Resurfacing costs less when the lot can take it. One national cost guide says resurfacing suits pavement under 15 to 20 years old. The lot also needs a good foundation and less than 30 percent surface damage. Asphalt resurfacing puts a new layer of hot mix over the sound pavement, with low spots leveled first.
A failed base is a different job. Georgia DOT’s resurfacing guide says isolated base failures must be corrected by full-depth patching. That replaces both base and pavement in the small area affected. The guide calls widespread cracking in the wheel paths clear evidence of inadequate structural strength. Overlaying distress that extensive is not cost-effective, it says.
On a lot, the wheel paths are the drive lanes where cars and trucks run. A few failed spots in a sound lot are asphalt repair work. We cut out the failed area, rebuild the base where it failed and patch it with hot mix. Failure spread across the lanes points to replacing the lot from the base up.
What do parking lot sealcoating and striping cost over time?
One national guide says asphalt lots are commonly sealcoated every two to five years. At $0.14 to $0.25 per square foot, the 50-space example comes to about $2,100 to $4,375 each time.
Striping lasts about 2 to 5 years, another guide says. Sealer covers the old lines, so after sealcoating we restripe the lot. Our parking lot striping repaints the stalls, arrows, crosswalks and accessible spaces.
A new layout costs 20 to 50 percent more to paint than restriping the existing lines. Most striping estimates also carry a mobilization fee of about $150 to $350.
What should a parking lot paving estimate spell out?
A written estimate should say what it includes, so bids can be compared. The asphalt paving industry’s national trade group says a contract should include the thickness of the pavement. It should also set out the responsibilities for site preparation and drainage.
On a parking lot, look for these lines:
- The square footage to be paved, resurfaced or sealed
- The base work: grading, stone base and compaction
- The thickness, with heavier sections where trucks run
- The drainage, and where the water goes
- The striping layout and the accessible spaces
- The phasing, if the business stays open during the work
Our estimates spell out the thickness, the base work and the square footage for your job.
How do you get a price for your parking lot?
Every figure here is a market number, not our price list. We pave new lots and resurface, patch, sealcoat and restripe existing ones. We are based in Cartersville and work for businesses, churches, shops and HOAs across Northwest Georgia. More of that work is on our commercial paving page.
We come out, look at the lot, measure it and give you an estimate that spells out the scope. Call or text (706) 844-2123, or read more about parking lot paving.